New Building Construction Update 7/31/2019

August 1st, 2019 by

Macuch Steel wrapped up their structural work last week finishing moment welds, decking, and studs. The team did a great job working quickly and safely to finish ahead of schedule!

 

O’Cain concrete had an early morning pour last week placing the second-floor slab. However, after getting some rest, the team jumped to the first floor to begin prep for the upcoming slab on grade pour.

 

O’Cain plumbing was able to complete rough-in and pass their underground inspection, allowing the concrete crew to roll right into a slab on grade prep.

 

Watson Electrical is working on wrapping up their underground rough-ins. Once they complete their floor boxes and turn-ups into the electrical room, they will be ready for inspection.

Upcoming Construction:

  • Complete underground electric rough-in
  • Fine grade first-floor slab
  • Termite protection
  • Prep slab on grade
  • Pour slab on grade
  • Begin exterior framing
  • Install metal pan stairs
  • Install roof curbs
Posted in New Facility