With cooperative weather in Charleston this week, the Baker INFINITI project has made forward progress. O’Cain Construction formed and poured two critical concrete lintels to ensure Citadel could continue laying block.

Watson Electric finished slab underground rough-ins and called for City inspection. Most importantly, they were able to get the first floor electrical room laid out and stubbed up for slab-on-grade placement.

Citadel Masonry was able to progress this week as they near top-out on the west elevation and began the south elevation.  The building is beginning to take shape as it comes out of the ground, something everyone is pleased to see!

 

Upcoming Construction:

  • Finish last two spread footers
  • Continue CMU walls and steel embeds
  • Begin structural steel erection