New Building Construction Update 5/28/2019

May 28th, 2019 by

Good news in Charleston, we received our building permit last Thursday! With permit in hand, we are now able to move forward with construction.

 

Earlier in the week, the building corners were confirmed, rebar was delivered and the existing slab was cut for a clean tie into the existing service building.

 

 O’Cain construction was able to start footers last Thursday and is progressing. They are planning to have all footers complete by the end of this week.

 

Upcoming construction:

  • Finish excavation of footers and rebar install.
  • Set anchor bolts.
  • Place continuous and spread footings.
  • Begin CMU walls.
  • Underground rough-ins.
Posted in New Facility