Baker INFINITI Charleston Construction Update 10/28/2019
Grey Interiors wrapped up finishing the walls and hang hanging millwork blocking.
Quantum Coatings followed right behind finished drywall priming all available walls.
Out front, Craven installed exterior aluminum storefront and O’Cain is working to rough grade the front parking lot for pervious pavers.
CSW is continuing with air barrier and their stucco system on the Mercedes side of the building.
Upcoming Construction