The Baker INFINITI mock-up is coming along nicely and will be looking for city approval shortly.

In wall rough-ins are nearly complete and above ceiling rough-ins are in progress for all MEP trades.

CSW is progressing with air barrier and their stucco system around the back and sides of the building.

 

Grey interiors is working on topping out second floor walls, keeping all of our MEP trade partners moving along.

Grey Interiors getting ready to frame the hard ceilings.

Upcoming Construction

  • Complete in-wall MEP rough-in
  • Begin air barrier and stucco
  • Continue above ceiling rough-in
  • Start up RTU’s
  • Complete top out and hang walls