Construction Update 01/20/2020

January 20th, 2020 by

Baker INFINITI Charleston
Construction Update 1/20/2020

The Baker INFINITI project is nearly to the finish line, thanks to the hard work of our trade partners.

On the interior, floor tile and carpet have been laid and quartz tops have been set. At the back service drive, new tile was laid where out temporary wall tied into the existing building.

Additionally final inspections are underway and should be complete within the next few days.

On the exterior, the glass curtainwall sail is complete and the parking lot was cleaned and striped.

Upcoming Construction

  • Complete millwork panels
  • Complete final inspections
  • Final clean
  • Punch list
  • Owner turnover

Monteith Construction | 910.791.8101 | www.MonteithCo.com

Posted in New Facility