The Baker INFINITI project is racing to the finish line, thanks to the hard work of our trade partners.
|
|
|
On the interior, finishes are well underway with tile and millwork panels being put in place.
|
|
|
On the exterior, CSW has complete their stucco. Craven Glass is erecting the glass curtainwall sail and installing the Euro-Wall at the New Vehicle Delivery.
|
|
|
Upcoming Construction
- Erect curtainwall sail
- Complete glass install
- Complete floor tile
- Complete carpet tile
- Complete millwork panels
- Point-up and final paint
|
|
|
|
|
|
|