New Building Construction Update 10/07/2019
|
Baker INFINITI Charleston
Construction Update 10/7/2019
|
|
|
The Baker INFINITI mock-up is coming along nicely and will be looking for city approval shortly.
|
|
|
In wall rough-ins are nearly complete and above ceiling rough-ins are in progress for all MEP trades.
|
|
|
CSW is progressing with air barrier and their stucco system around the back and sides of the building.
|
|
|
Grey interiors is working on topping out second floor walls, keeping all of our MEP trade partners moving along.
|
|
|
Grey Interiors getting ready to frame the hard ceilings.
|
|
|
Upcoming Construction
- Complete in-wall MEP rough-in
- Continue air barrier and stucco
- Continue above ceiling rough-in
- Start up RTU’s
- Complete top out and hang walls
|
|
|
|
|
|
|